COFRIN TECHNOLOGY & EDUCATION CENTER CONSTRUCTION

Project Timeline

Learn More

2020 Cofrin Library Renovation & Use Study

A 2020 study concluded that a replacement building will be more cost effective and better able to meet the community’s current and future needs.

See Site Information

$96.3 Million in State Funding

On June 8, 2021, state funding for the Cofrin Library construction project was approved in 2021 Wisconsin Act 58 at $96,297,000 ($93,850,000 GFSB and $2,447,000 PRSB).

UW-Green Bay News Story

2021 Wisconsin Act 58

Final Designs: Fall 2024

Final construction plans are due to be finalized and submitted in Fall 2024.

Building Plans

Bidding: January 2025

We issue for bids in December 2024. Bids are due January 2025 with notice to proceed in March 2025.

Break Ground: Spring 2025

Plans include a target construction start date in April 2025 through January 2027. Construction phase runs 22 months.

Completion: January 2027

The substantial completion milestone is set for January 2027. Move-in is scheduled for February and March 2027.

Campus Restoration: 2027

This 7-month phase runs April through October of 2027. It includes demolition of the old Cofrin Library building, finishing entrances to the tunnels and landscaping.

Construction Project Updates

To keep the campus community apprised of the latest updates and details regarding the Cofrin Technology & Education Center, we have created a special information site. This is where project organizers will post communication about closures, construction, demolition and more as the project timeline progresses.