Six Year Plan for 2005-2007 Biennium

2005 - 2007 Biennium

PriorityProject NameProject DescriptionFund SourceEstimated Cost
1Phoenix Sport Center Construction

Project currently approved for planning and design.

Construct a 4,000 seat multi-purpose space for athletic and intramural events, along with support spaces. Remodel some of the existing building.GPR/
PR/Gift
$27 Million
2University Union Construction

Project currently in a program feasibility study.

Remodel existing spaces and construct new spaces to accommodate retail venues, dining, and student programs.PR/Gift$6 Million
3West Wing Renovation – Planning / Construction (Rose and Wood Hall)Remodel both buildings to suit UWGB Administration, Social Work, and general assignment classroom spaces.GPR$5 Million


2007 - 2009 Biennium

PriorityProject NameProject DescriptionFund
Source
Estimated
Cost
1Cofrin Library Remodeling – Planning / ConstructionRemodel several floors to accommodate circulation patterns and organization within the Library.GPR$7.5 Million


2009 - 2011 Biennium

PriorityProject NameProject DescriptionFund
Source
Estimated
Cost
1
Not submitted or defined yet.GPR/Gift$30 Million


Two Year All Agency Projects 2005 - 2007 Biennium

PriorityProject NameProject DescriptionFund
Source
Estimated
Cost
1Instructional Services HVAC/Electrical UpgradeModify 1/3 of the mechanical room and remodel 20,000 gsf of office space.GPR

$2,450,000

2Student Services Mechanical / RemodelingPulverize and regrade existing pavement. Pave both roads and install new aggregate for shoulders.GPR$1,500,000
3Studio Arts / Theatre Hall Infrastructure and RemodelingPulverize the courts and base. Repair drain tile and regrade as necessary. Reconstruct six courts.GPR$1,450,000